Disassembly Siemens 3.6 MW

A major scale turn-key project. Following many years of providing full-service maintenance, we disassembled a Siemens 3.6 MW and prepared it for transport. This wind turbine will be given a new lease of life in Africa.

back to project overview

WIERINGERMEER DISASSEMBLY

Project planning, engineering, transport and practice. This kind of project requires the perfect blend. Commissioned by one of our clients, we disassembled a Siemens 3.6 MW in Wieringermeer, the Netherlands.

 

 

“An enormous logistical operation”

 

With minute precision, all components were disassembled, packaged, and ordered – thereby immediately preparing for reassembly in Africa.

A logistical operation that used big cranes and specialised roadway transport, and even went across the water.

 

Projectgegevens

  • Product Siemens 3.6 MW
  • Activities Turn-Key disassembly
  • Country Netherlands
  • Place Wieringermeer
  • DestinationAfrica