From overhaul to full output β 5x E70
We took care of nearly the entire scope. Five Enercon E70 turbines were overhauled in our workshop and prepared for renewed operation. In parallel, we installed a new substation, managed all cabling and connections, and ensured smooth commissioning.
With strong winds forecasted on the build day, we decided to carry out part of the work at night to stay on schedule. Thanks to the solid collaboration with Koppejan Wind Service, who handled the turbine assembly, the project was delivered on time.
back to project overviewLooking for a hassle-free turbine project? Letβs connect!
π Ballytoag Windfarm
π 5x Enercon E70 overhauled
π€ In collaboration with Koppejan Wind Service